Content Handover Meeting minutes - April 2023 International Edition
Content Handover Meeting minutes - April 2023 International Edition
2025-Sep-09
Date of Initial Handover meeting: 13 April 2023
Date of Final Handover meeting: 18 April 2023
Attendees
@Andrew Atkinson (AAT)
@Maria Braithwaite (MBR)
@Donna Morgan (DMO)
@Chris Morris(CMA)
@Joe Cameron-Schofield(JSC)
Handover Status
FINAL HANDOVER COMPLETE
Agenda
Items to be discussed
Actions
Items to be discussed
Actions
1
Prerelease Content Management Activities:
Inactivate the root concept synonym referencing previous release, and add synonym to reference current release.
Update copyright date on synonym (January releases only)
Generate + Validate SEP Refsets
Generate + Validate Lateralizable Refset
Content Team to confirm to Release Manager that 4x MRCM refset files are complete and ready to be released (they are then extracted from the termServer during release builds via the termServer Export)
Traceability March 2023 release - NONE on MAIN (2 failures found on project confirmed false positives not seen in daily build after promotion https://jira.ihtsdotools.org/browse/INFRA-10533)
Instead of usual manual Content validation, we now just need confirmation that all Projects had automated validation run against them, and were clean before promotion.
New Issues identified by the community from the previous Monthly Release.
Decision on whether to fix the issues:
VERY QUICKLY in time for this upcoming release?
In good time for the next monthly release?
Content Release Lead confirms to Release Manager that all Projects had automated validation run against them, and all issues identified were resolved before promotion - failures for lateralizable reference set all false positives https://projects.jira.snomed.org/browse/INFRA-10756
ICD-10 - expecting 550 ish changes (plus tonight's drip feed) due to large number of intentional inactivations this cycle
No expected issues this cycle...
Confirmed in final numbers!
February 2023:
ICD-0 - 1 new records + 0 inactivations expected
ICD-10 - expecting 500 ish changes (plus tonight's drip feed) due to large number of intentional inactivations this cycle
No expected issues this cycle...
Confirmed in final numbers!
March 2023:
ICD-0 - 2 new records + 0 inactivations expected
ICD-10 - expecting 315 ish changes (plus tonight's drip feed) due to large number of intentional inactivations this cycle
No expected issues this cycle...
Confirmed in final numbers!
April 2023:
ICD-0 - 6 new records + 2 inactivations expected
+ for the specific fixes for this cycle we're expecting 7 records that should have been inactivated in March but were not, but should be now
+ Rick is going to tweak the Mapping Dashboard to give Donna more visibility of the final expected map figures (EXCLUDING "no target" maps which she would normally include in her figures but which we wouldn't see coming out of the Delta files)
ICD-10 - expecting 537 ish changes (plus tonight's drip feed) due to large number of intentional inactivations this cycle
No expected issues this cycle...
Confirmed in final numbers!
***** NOTE: Make sure that we keep an eye on the upgrade to ICD-0 version 3.2/3.4, as it "MAY" happen at some point in 2023 *****
5
Brief run through of the known issues already identified by the content team during the QA batch process, to ensure that technical team are aware of them, and can either resolve them in time for the release, or confirm as known issues.
6
DevOps resource confirmed
7
Versioning and Change Freeze
Plan is to follow the new processes as now defined:
For information - there has been a P1 issue with validation in the authoring platform, this has meant that there have been no project promotions with content since 6 April 2023, the patch deployment was made today, details here https://projects.jira.snomed.org/browse/FRI-641 I had to promote a project this morning to fix a content issue and the validation ran without a problem, the daily build RVF report has also been run this morning and has completed, no issues (other than known issues) found.