July 2019 International Edition Release Schedule - INTERNAL
Date | Responsibility | Deliverables |
---|---|---|
Nov 12, 2018 | @Maria Braithwaite | Authoring begins for the July 2019 International Edition editing cycle. |
Mar 1, 2019 | @Yongsheng Gao | Content team to deliver final MRCM change requests to EPS Team for action |
Mar 8, 2019 | @Former user (Deleted) | EPS Team delivers MRCM changes to content team for review - Content Team to complete this by Mar 13, 2019 |
Mar 13, 2019 | @Yongsheng Gao | Content team to deliver final reviewed MRCM changes plus any feedback to EPS Team |
Mar 13, 2019 | @Former user (Deleted) | EPS Team to make any necessary changes (based on feedback from the authors) and verify with Content Team by Mar 15, 2019 |
Mar 15, 2019 | @Jane Millar | Cut off for external collaboration partner CRS Requests (IHE, HL7, etc) - set date of 15th March + 15th September each cycle for clarity |
Mar 15, 2019 | @Former user (Deleted) | NO FURTHER MRCM CHANGES ACCEPTED - everyone has agreed this, with the caveat that any critical changes can be reviewed by all of us in order to analyse impact vs business case and allow a change if absolutely necessary. |
Mar 18, 2019 | @Andrew Atkinson | Final MRMC refsets delivered by EPS Team to Release Management team for review |
Mar 18, 2019 | @Kai Kewley | SNOMED International Tech Team to now:
|
Apr 5, 2019 | @Maria Braithwaite | NO FURTHER CRS REQUESTS ACCEPTED (Single content request cut off) |
Apr 19, 2019 | @Maria Braithwaite |
|
Apr 30, 2019 | @Maria Braithwaite |
|
May 2, 2019 | @Maria Braithwaite | Content team review, rebase and finalise all content |
May 2, 2019 | @Maria Braithwaite | Content team promote to MAIN final content for all projects to be released in the current editing cycle (weekend contingency) |
May 3, 2019 | @Maria Braithwaite | Content Release Lead to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover. |
May 3, 2019 | @Maria Braithwaite @Farzaneh Ashrafi + @Suzanne Santamaria | Final content review (2 days - BEWARE OF BANK HOLIDAY ON 6th May 2019!) Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement |
May 8, 2019 | @Maria Braithwaite |
|
May 8, 2019 | @Andrew Atkinson | Planned Initial Handover meeting |
May 8, 2019 | @Donna Morgan |
|
May 8, 2019 | @Kai Kewley + @Yongsheng Gao | Transition from Stated Relationships to OWL refsets + Validation of the new complete OWL refsets |
May 10, 2019 | @Terance Shird | termServer branching and Release versioning |
May 11, 2019 | @Andrew Atkinson | Full validation of the initial exported content, including the new OWL refsets |
May 13, 2019 | @Yongsheng Gao |
|
May 14, 2019 | @Maria Braithwaite |
|
May 15, 2019 | @Donna Morgan |
|
May 15, 2019 | @Andrew Atkinson |
|
May 15, 2019 | @Maria Braithwaite | Handover of Release Notes to technical team Release manager |
May 22, 2019 | @Andrew Atkinson | PLANNED Alpha Release date Restart validation in SCA (no longer relevant - new process should allow validation to re-start immediately when Content authoring starts for next editing cycle) |
May 31, 2019 | @Andrew Atkinson | PLANNED Alpha feedback deadline |
Jun 5, 2019 | @Andrew Atkinson | PLANNED BETA Release date |
Jun 14, 2019 | @Andrew Atkinson | PLANNED BETA feedback deadline |
Jun 30, 2019 | @Andrew Atkinson | Member Release date |
Jul 31, 2019 | @Andrew Atkinson | Public Release date |