Mapping Generation process (ICD-0 + ICD-10) - November 2021

Mapping Generation process (ICD-0 + ICD-10) - November 2021



Date

Time (UTC)

Responsibility

Action / Deliverables

Date

Time (UTC)

Responsibility

Action / Deliverables

Nov 3, 2021 

12:00

Devops

Setup new automated JIRA tickets to be generated from the parent International Release ticket, for all Mapping steps below (both internal and external)

Nov 15, 2021 

12:00

SI Mapping Team

Mapping team to finalise any last mapping from the final content that came through after 12:00 content cut off (or any issues identified during the Release Mapping Server validation process), and then Resolve their "Mapping Complete" ticket to confirm that "Mapping QA complete".

Nov 15, 2021 

12:30

SI Mapping Team

WCI (External Team)

12:30 - MAPPING CUTOFF

This is using the content from last night's Daily Build feed (run at 01:00).

Nov 15, 2021 

12:30

SI Content Team

WCI (External Team)

12:30 - SI Content Team to create 2x new Tasks in snowStorm, to accept the upload of the new Map files Delta's (one for SimpleMap + one for ExtendedMap delta files)

Nov 15, 2021   

12:30

SI DevOps Team

Snapshot used to provisionally bring the AP validation etc back up again today, so that it works for the interim period until the new Production release package is signed off tomorrow (on the 15th October this cycle)...

Nov 15, 2021 

12:30

SI Content Team

12:30 - Content Team Release Lead (@Maria Braithwaite) to confirm definitively that nothing has been authored (that requires mapping) since the final Daily Build was run.  If it was, the emergency process needs to be invoked (see below)...

Nov 15, 2021 

13:00

Devops

Manual/automated backup of Mapping Server 

@Chris Morris to automate when possible...

Nov 15, 2021 

14:00

WCI (External Team)

Mapping Server Cloned over to the Release Mapping Server

In future, this should happen immediately after the backup of the Mapping Server is complete, if this can be automated?

RW 2021-11-15: This step is being skipped, unless issues are identified with the maps (see bottom row "If there is a Critical (P1) issue found...")

Nov 15, 2021 

14:00

WCI (External Team)

*** DRIP FEED SUSPENDED from this point onwards  (planned for tonight only) ***

Nov 15, 2021 

15:00

WCI (External Team)

ICD-0 + ICD-10 map files are then generated by WCI and QA reports checked

Potential for some discussion with Donna if any red flags in these reports...

Nov 15, 2021 

16:00

WCI (External Team)

ICD-0 + ICD-10 map files sent to technical team Release manager (Andrew Atkinson) before close of play

Nov 15, 2021 

16:00

WCI (External Team)

ICD-0 + ICD-10 FINAL map files (with BLANK EFFECTIVETIMES) uploaded to the termserver by WCI, using the RF2 Swagger upload process 

RW 2021-11-15: WCI staff got a 403 Access Denied error when trying to create the import for the map files.  https://snomed.atlassian.net/browse/INFRA-7907 created to look into what's happening.

LESSONS LEARNED FOR NEXT TIME:

  1. WCI do not have permissions to run swagger!  Should we show Maria how to do it? 

    1. OR, CAN WE SET Authoring permissions on JUST THIS PROJECT for WCI each cycle??

  2. Files MUST BE IMPORTED WITH BLANK EFFECTIVETIMES!!  Otherwise we can't then export them from the termserver!

Nov 15, 2021 

16:30

SI Content Team

SI Content Team to validate + promote the two Map file tasks

Nov 16, 2021 

02:00

WCI (External Team)

Cron job to completely remove SNOMED + upload the latest version to the Release Mapping Server.

In future, this should happen immediately after the Daily Build/Snapshot provided by DevOps post-versioning is available, if @Rick Wood  can automate this?

RW 2021-11-16: this was done Nov 15th after the 1:00 Daily Build, since this was after authoring cut-off and contained all content for the release.

Nov 16, 2021 

03:00

WCI (External Team)

WCI to validate the Release Mapping Server

RW 2021-11-16: no longer using the release mapping server unless issues are identified with the maps (see bottom row "If there is a Critical (P1) issue found...")

Nov 16, 2021 

04:00

WCI (External Team)

WCI to lift maintenance window and allow Mapping Team to access other projects ONLY (GMDN, MedDRA, etc)

Nov 16, 2021 

13:00

SI Release Team

Technical team Release manager builds and validates a new Pre-Production release based on the new versioned content, which now includes both ICD-0 and ICD-10 map content.

***** MANIFEST MUST BE CHANGED TO PULL MAP FILE DATA FROM SNOWSTORM INSTEAD OF EXTERNALLYMAINTAINED FOLDERS ******

Nov 16, 2021  

15:00

SI Release Team

Once Final, versioned Release Build is signed off by Release Manager, it is handed over to DevOps to update the Daily Build, plus all AP validations, etc

As this can take a few days (depending on when the weekends fall this cycle, etc), in the interim DevOps will use the provisional Snapshot release from the versioning process in order to ensure minimal downtime for these services.

Nov 16, 2021 

18:00

WCI (External Team)

*** Mapping Drip feed is restarted  ***

Nov 17, 2021

02:00

Automated

Daily Build runs for the first time since the initial cut off. 

Mapping Drip feed runs for the first time since the initial cut off.

Nov 17, 2021 

09:00

SI Mapping Team

SI Mapping Team are able to re-start work for the next cycle

Oct 18, 2021  

09:00

Everyone

DR PLAN:  If there is a Critical (P1) issue found in either the Map files or the final SNOMED CT content (shouldn't be due to the new task/project validation, but we need an emergency process just in case), then WCI can import a specific fix branch straight into the Cloned Release Mapping Server, without bleed through from the next month's content.  However, this should only be used in the genuine emergency situations...

Copyright © 2025, SNOMED International