July 2021 International Edition Release Schedule - INTERNAL
Date | Responsibility | Deliverables |
---|---|---|
Nov 25, 2020 | @Maria Braithwaite | Authoring begins for the July 2021 International Edition editing cycle. |
Mar 15, 2021 | @Jane Millar | Cut off for external collaboration partner CRS Requests (IHE, HL7, etc) - set date of 15th March + 15th September each cycle for clarity. |
Mar 16, 2021 | @Yongsheng Gao | NO FURTHER MRCM CHANGES ACCEPTED - everyone has agreed this, with the caveat that any critical changes can be reviewed by all of us in order to analyse impact vs business case and allow a change if absolutely necessary. The final state of all MRCM resets will then automatically be included in both authoring validation + release. |
Apr 5, 2021 | @Maria Braithwaite | NO FURTHER CRS REQUESTS ACCEPTED https://www.snomed.org/snomed-ct/Use-SNOMED-CT/change-or-add |
May 4, 2021 | @Maria Braithwaite |
|
May 11, 2021 | @Maria Braithwaite |
|
May 11, 2021 | @Andrew Atkinson | Pre-close of release full validation of the initial exported content. |
May 12, 2021 | @Maria Braithwaite | Content team review, rebase and finalise all content for July 2021 release. |
May 13, 2021 | @Maria Braithwaite | Content team promote to MAIN final content for all projects for the July 2021 release. |
May 14, 2021 | @Maria Braithwaite | Content Release Lead to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project (INTQA) - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover. |
May 14, 2021 | @Maria Braithwaite @Farzaneh Ashrafi + @Suzanne Santamaria | Final content review (2 days). Request vet extension report. Request QI project content changes report. Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement. |
May 18, 2021 | @Maria Braithwaite |
|
May 18, 2021 | @Andrew Atkinson / @Maria Braithwaite | Planned Initial Handover meeting. |
May 18, 2021 | @Donna Morgan |
|
May 19, 2021 | @Terance Shird | termServer branching and Release versioning - Technical Team Release tasks - July 2021 |
May 20, 2021 | @Andrew Atkinson | Full validation of the initial exported content. |
May 20, 2021 | @Yongsheng Gao |
|
May 21, 2021 | @Andrew Atkinson @Donna Morgan @Maria Braithwaite |
|
May 21, 2021 | @Donna Morgan |
|
May 24, 2021 | @Andrew Atkinson |
|
May 25, 2021 | @Maria Braithwaite | Handover of Release Notes to technical team Release manager (note: recheck final figures for concepts changes/ additions etc before member release and public release to take into account changes made after close of editing. |
Jun 9, 2021 | @Andrew Atkinson | PLANNED BETA Release date. Restart the mapping Drip Feed - this can actually be done earlier than the final Beta if required, as the only pre-requisite is to complete the ICD-0/ICD-10 testing in the Beta build. This is simply to provide confidence that there will not likely be map changes during the Beta stage, which could in theory create re-work for the teams. This risk should be balanced against the growing backlog of map changes, and a decision made whether to use an early Beta build to switch the drip feed back on. |
Jun 16, 2021 | @Andrew Atkinson | PLANNED BETA feedback deadline. Last day for addition of COVID-19 related vaccine concepts (critical content only). |
Jun 30, 2021 | @Andrew Atkinson | Member Release date. |
Jul 31, 2021 | @Andrew Atkinson | PRODUCTION Public Release date. |