Date | Responsibility | Deliverables |
---|---|---|
May 15, 2019 | @Maria Braithwaite | Authoring begins for the January 2020 International Edition editing cycle. |
Sep 2, 2019 | @Yongsheng Gao | Content team to deliver final MRCM change requests to EPS Team for action |
Sep 6, 2019 | @Former user (Deleted) | EPS Team delivers MRCM changes to content team for review - Content Team to complete this by Sep 11, 2019 |
Sep 11, 2019 | @Yongsheng Gao | Content team to deliver final reviewed MRCM changes plus any feedback to EPS Team |
Sep 13, 2019 | @Former user (Deleted) | EPS Team to make any necessary changes (based on feedback from the authors) and verify with Content Team by Sep 13, 2019 |
Sep 15, 2019 | @Jane Millar | Cut off for external collaboration partner CRS Requests (IHE, HL7, etc) - set date of 15th March + 15th September each cycle for clarity |
Sep 15, 2019 | @Former user (Deleted) | NO FURTHER MRCM CHANGES ACCEPTED - everyone has agreed this, with the caveat that any critical changes can be reviewed by all of us in order to analyse impact vs business case and allow a change if absolutely necessary. |
Sep 18, 2019 | @Andrew Atkinson | Final MRMC refsets delivered by EPS Team to Release Management team for review |
Sep 18, 2019 | @Kai Kewley | SNOMED International Tech Team to now:
|
Oct 3, 2019 | @Maria Braithwaite | NO FURTHER CRS REQUESTS ACCEPTED (Single content request cut off) |
Oct 18, 2019 | @Maria Braithwaite |
|
Oct 31, 2019 | @Maria Braithwaite |
|
Nov 1, 2019 | @Maria Braithwaite | Content team review, rebase and finalise all content |
Nov 1, 2019 | @Maria Braithwaite | Content team promote to MAIN final content for all projects to be released in the current editing cycle (weekend contingency) |
Nov 4, 2019 | @Maria Braithwaite | Content Release Lead to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover. |
Nov 4, 2019 | @Maria Braithwaite @Farzaneh Ashrafi + @Suzanne Santamaria | Final content review (2 days) Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement |
Nov 8, 2019 | @Maria Braithwaite |
|
Nov 8, 2019 | @Andrew Atkinson / @Maria Braithwaite | Planned Initial Handover meeting *** Maria to cover whilst Andrew is away |
Nov 8, 2019 | @Donna Morgan |
|
Nov 11, 2019 | @Terance Shird | termServer branching and Release versioning |
Nov 13, 2019 | @Andrew Atkinson | Full validation of the initial exported content (to be done during last week of October due to annual leave in November this year) |
Nov 13, 2019 | @Yongsheng Gao |
|
Nov 14, 2019 | @Maria Braithwaite |
|
Nov 15, 2019 | @Donna Morgan |
|
Nov 15, 2019 | @Maria Braithwaite | Handover of Release Notes to technical team Release manager |
Nov 18, 2019 | @Andrew Atkinson |
|
Nov 29, 2019 | @Andrew Atkinson | PLANNED Alpha Release date Restart validation in SCA (no longer relevant - new process should allow validation to re-start immediately when Content authoring starts for next editing cycle) |
Dec 5, 2019 | @Andrew Atkinson | PLANNED Alpha feedback deadline |
Dec 6, 2019 | @Andrew Atkinson | PLANNED BETA Release date |
Dec 13, 2019 | @Andrew Atkinson | PLANNED BETA feedback deadline |
Dec 31, 2019 | @Andrew Atkinson | Member Release date |
Jan 31, 2020 | @Andrew Atkinson | Public Release date |