Nov 18, 2019 

@Maria Braithwaite

Authoring begins for the July 2020 International Edition editing cycle.

Mar 2, 2020 

@Yongsheng Gao

Content team to deliver final MRCM change requests to EPS Team for action

Mar 6, 2020 

@Former user (Deleted)

EPS Team delivers MRCM changes to content team for review - Content Team to complete this by Mar 11, 2020 

Mar 11, 2020 

@Yongsheng Gao

Content team to deliver final reviewed MRCM changes plus any feedback to EPS Team

Mar 13, 2020 

@Former user (Deleted)

EPS Team to make any necessary changes (based on feedback from the authors) and verify with Content Team by Mar 13, 2020 

Mar 15, 2020 

@Jane Millar

Cut off for external collaboration partner CRS Requests (IHE, HL7, etc) - set date of 15th March + 15th September each cycle for clarity

Mar 16, 2020 

@Former user (Deleted)

NO FURTHER MRCM CHANGES ACCEPTED - everyone has agreed this, with the caveat that any critical changes can be reviewed by all of us in order to analyse impact vs business case and allow a change if absolutely necessary.

Mar 18, 2020 

@Andrew Atkinson

Final MRMC refsets delivered by EPS Team to Release Management team for review

Mar 18, 2020 

@Kai Kewley

SNOMED International Tech Team to now:

  1. add UUIDs to the MRCM google sheet for all new MRCM rules, and

  2. update the MRCM in the SCA to ensure remaining new cycle content validated against the latest version.

????? NO LONGER REQUIRED due to MRCM Tool????????

Apr 5, 2020 

@Maria Braithwaite

NO FURTHER CRS REQUESTS ACCEPTED

Apr 24, 2020 

@Maria Braithwaite

  • NO FURTHER BATCH LOADS OR BULK UPDATES

  • NO FURTHER PROMOTION FOR PROJECTS THAT HAVE LARGE SCALE CHANGES - For example this would include large scale changes to foundational hierarchies such as anatomy or substances, or changes that are likely to have impact to reports such as the pattern report (e.g. redundant relationships) or MRCM (e.g. cardinality issues in legacy content where edits have been made to that content without resolving the pre-existing cardinality issue).

Apr 30, 2020 

@Maria Braithwaite

  • Last day for authors to launch new tasks in SCA - no more new tasks launched after this date,

  • Verify all new namespace concepts have been added

  • Early Visibility Handover meeting (if complexity of Release requires)

Apr 30, 2020 

@Andrew Atkinson

Pre close of release full validation of the initial exported content

May 1, 2020 

@Maria Braithwaite

Content team review, rebase and finalise all content

May 1, 2020 

@Maria Braithwaite

Content team promote to MAIN final content for all projects to be released in the current editing cycle (weekend contingency)

May 4, 2020 

@Maria Braithwaite

Content Release Lead to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover.

May 4, 2020 

@Maria Braithwaite





@Farzaneh Ashrafi + @Suzanne Santamaria

Final content review (2 days)

Request vet extension report

Request QI content changes report

Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement

May 7, 2020 

@Maria Braithwaite

  • CONTENT CUTOFF DATE (12:00 UTC), +

  • Handover of content to technical team Release manager

  • Content Release Lead to request (via Infra ticket) the maintenance screen to be raised in Production, to prevent further updates to International content - Technical Team Release tasks - July 2020

  • Reminder to WCI to cut off mapping drip feed (but NOT clone over to Release Server until Mapping Team confirms that both ICD-0/ICD-10 + GMDN maps are all updated based on 8th Content + latest GMDN content

May 7, 2020 

@Andrew Atkinson /

@Maria Braithwaite

Planned Initial Handover meeting

May 7, 2020 

@Donna Morgan

  • Mapping Team to notify WCI mapping/review ready for QA

  • QA of mapping (Mapping Team + WCI)

May 11, 2020 

@Terance Shird

termServer branching and Release versioning - Technical Team Release tasks - July 2020

May 13, 2020 

@Andrew Atkinson

Full validation of the initial exported content

May 13, 2020 

@Yongsheng Gao

  • Content Team to confirm that Lateralizable refset is complete in Production refset tool (Release manager to then action the refset tool release to get the delta files), +

  • Content Team to deliver the SEP refsets (x2) to Release manager

May 14, 2020 

@Maria Braithwaite

  • Mapping/Review/Technical QA complete

  • Authors and mappers - Preparation of release notes content 

May 15, 2020 

@Donna Morgan

  • MAPPING CUTOFF DATE (12:00 UTC), +

  • Mapping team to request Clone of Mapping content (both ICD-0/ICD-10 + GMDN) over to the Release Server, in order to provide a stable baseline for both upcoming International + GMDN releases.

  • Handover of ICD-0 + ICD-10 maps to technical team Release manager (@Andrew Atkinson)

May 15, 2020

@Maria Braithwaite

Handover of Release Notes to technical team Release manager

May 18, 2020 

@Andrew Atkinson

  • Planned Final Handover meeting, +

  • PLANNED Early Alpha Release date

  • Provisional date for Content authoring starts for next editing cycle

May 29, 2020 

@Andrew Atkinson

PLANNED Alpha Release date

Restart the mapping Drip Feed - this can actually be done earlier than the final Alpha if required, as the only pre-requisite is to complete the ICD-0/ICD-10 testing in the Alpha build. This is simply to provide confidence that there will not likely be map changes during the Alpha/Beta stage, which could in theory create re-work for the teams. This risk should be balanced against the growing backlog of map changes, and a decision made whether to use an early Alpha build to switch the drip feed back on.

Restart validation in SCA (no longer relevant - new process should allow validation to re-start immediately when Content authoring starts for next editing cycle)

Jun 5, 2020 

@Andrew Atkinson

PLANNED Alpha feedback deadline

Jun 10, 2020 

@Andrew Atkinson

PLANNED BETA Release date

Jun 17, 2020 

@Andrew Atkinson

PLANNED BETA feedback deadline

Jun 30, 2020 

@Andrew Atkinson

Member Release date

Jul 31, 2020 

@Andrew Atkinson

Public Release date